STUDENT CENTER 2121 Euclid Avenue McKEE BUILDING (also named Student Center) 2300 Euclid Avnue 7/22/71 (71-58) Approved preliminary renovation plans of the McKee South Building 2301 Euclid Ave., and established a $360,000 project budget. 3/16/72 (72-20) Awarded construction contracts for renovation of the McKee South Building: general work: Cleary Construction $153,718 electrical Consoildated Comstock 82,870 HVAC Reliance 33,083 plumbing Gorman-Lavelle 19,490 3/24/72 (72-23) Awarded HVAC contract for renovation of the McKee South Building to Hatfield Mechanical Contractors, Inc. for $37,230. 9/17/75 (75-58) Approved the demolition of the Student Center to make room for the new Science & Research Center. 3/17/06 (06-15) Approved Braun & Steidl/Gwathmey Siegal as architect for the Student Center project. 1/26/07 (07-04) Approved construction management services contract with Heery International. 3/16/07 (07-19) Approved construction manager services contract with Heery International. 9/12/08 (Board Officers Resolution 2008-11) Approved the bid award to Mid American Construction, LLC for the Student Center foundation, structural steel, site utility and elevator package for $8,462,300, subject to the approval of the Ohio Attorney General. 3/9/09 (Board Officers' Resolution 2009-1, 1/12/09) Approved award bid for Panzica Co. for General Trades Work in connection with the Student Center Shell and Core Project. 3/9/09 (Board Officers' Resolution 2009-2, 1/12/09) Approved award bid to Gorman Lavelle Corp. for plumbing and fire protection work in connection with the Student Center Shell and Core Project. 3/9/09 (Board Officers' Resolution 2009-3, 1/12/09) Approved bid award to T. H. Martin, Inc. for HVAC work in connection with the Student Center Shell and Core Project. 3/9/09 (Board Officers' Resolution 2009-4, 1/12/09) Approved bid award to Lake Erie Electric, Inc. for electrical work in connection with the Student Center Shell and Core Project. 3/9/09 (Board Officers' Resolution 2009-5, 1/12/09) Approved bid award to US Communications for technology work in connection with the Student Center Shell and Core Project. 3/9/09 (Board Officers' Resolution 2009-6, 1/12/09) Approved bid award to Johnson Service Work for food service work in connection with the Student Center Shell and Core Project. 9/17/09 (Board Officers' Resolution 2009-12, 8/10/09) Approved bid award to Soundcom Systems for audio/visual work. 6/14/10 (10-37) Deferred $6.00/credit hour surcharge for ooprating expenses and debt service foy AY 2011. 3/25/14 (14-17) Approved gift announced at 2014 "Radiance" event that the Student Center ballroom named Glasscock Family Foundation Ballroom