PHYSICAL EDUCATION BUILDING 4/9/70 (70-21) Approved project for planning purposes and authorized request to release planning funds in accordance with policies of State Regents. 5/14/70 (70-32) Approved Flynn, Dalton, Van Dijk & Partners as Associate Architect for Physical Education Building project. 9/3/70 (70-55) Approved schematic design concept submitted by Flynn, Dalton & Van Dijk. 12/10/70 (70-83) Authorized administration to approve working drawings and final specifications for this project within limits of approved budget. 6/14/71 (71-46) Established construction budget totalling $9.1 million. 4/11/73 (73-15) Approved naming the Physical Education Building gymansium the Homer E. Woodling Gymnasium. 11/14/73 (73-59) Increased project budget from $9,170,000 to $9,270,000 for construction and furnishing of the Human Performance Laboratory. 11/13/74 (74-60) Increased total project budget by $40,000 from $9.27 to $9.31 million and specific budget for remaining expenditures in current biennium increased from $246,441 to $286,441. Approved transferring $40,000 from Student Union Reserve Funds to Physical Education Building Project to increase current capital budget. 11/13/74 (74-60) Concurred in award of construction contracts for completion of Human Performance Laboratory to firms recommended by Division of Public Works: General work R. Hansen & Co. $18,102 Mechanical work Heine Heating Co. 5,000 Electrical work LaCava Electrical Co. 3,900 Total $25,002 11/5/75 (75-71) Approved budget of $12,200 to complete construction, equipping, and furnishing of Human Performance Laboratory and Dance Studio areas. 5/3/89 (89-27) Appointed Evans and Associates, Inc as Associate Engineer for the $|00,000 pool filters replacement project. 5/3/89 (89-28) Appointed Roberts Consultants, Inc as Associate Engineer for the $|00,000 pool filters replacement project. 6/28/11 (11-42) Approved contract for repair of east wall masonry with H.M.H. Restoration, Ltd. 3/18/13 (13-14) Administration authorized to execute contract for construction services for roof replacement project. also see: Physical Plant Projects